Noida Unihomes – Construction Updates

Let us see what is happening on ground in NOIDA Unihomes.

Tower A1 – Phase1 : • Column casting (9th-floor) is under progress.  ‘A’ Block:- It comprises of four towers. Overall 80% of floors of this block have been raised. Around 25% of  brickwork has been done.

Tower a1

Tower a1

Tower B1 To B5 – Phase1 :  Internal plaster is under progress.  ‘B’ Block:- It comprises of five towers. All towers raised. Brickwork completed. Around 75% of plastering done. Other internal works being done. B1 tower is nearly complete.

Tower a1

Tower B

Tower C3 – Phase1 :  Top floor roof slab is complete. ‘C’ Block:- It comprises of four towers. All towers raised to their full height. Brickwork near completion.  Around 20% of plastering done.

Tower C3

Tower C3

Tower D2 – Phase2 :  Shuttering work for 5th floor roof is under progress.

Tower D2

Tower D2

BasemenT – Phase1 :  Lower & upper ground slab is under progress.  Parking:- A small portion of lower basement at one end remains to be completed, while work for upper basement has started from the other end.

BasemenT - Phase1

BasemenT – Phase1

BasemenT – Phase2 :  Lower basement roof slab is under progress.

BasemenT - Phase2

BasemenT – Phase2

Practically no progress in Phase II. F Block structure has already been completed. Around half of brickwork remains to be completed.

If the things keep moving at normal speed, phase 1 can be completed in eight months i.e. by March 2013.

Please feel free to leave your feedback on construction updates at unihomesbuyers@gmail.com or comment on section given below. This will help in circulating accurate and latest update on Unihomes construction progress.

One response

  1. tower B1 -ALMOST COMPLETE ?
    NO INSIDE FITTINGS AND GLASS WORK – GATES -WINDOW NOTHING WAS THERE-
    ONLY OUTSIDE SE JO DIKHTA HAI BAS VAHI HAI
    OR KUCH NAHI

Leave a comment