Let us see what is happening on ground in NOIDA Unihomes.
Tower A1 – Phase1 : • Column casting (9th-floor) is under progress. ‘A’ Block:- It comprises of four towers. Overall 80% of floors of this block have been raised. Around 25% of brickwork has been done.
Tower B1 To B5 – Phase1 : Internal plaster is under progress. ‘B’ Block:- It comprises of five towers. All towers raised. Brickwork completed. Around 75% of plastering done. Other internal works being done. B1 tower is nearly complete.
Tower C3 – Phase1 : Top floor roof slab is complete. ‘C’ Block:- It comprises of four towers. All towers raised to their full height. Brickwork near completion. Around 20% of plastering done.
Tower D2 – Phase2 : Shuttering work for 5th floor roof is under progress.
BasemenT – Phase1 : Lower & upper ground slab is under progress. Parking:- A small portion of lower basement at one end remains to be completed, while work for upper basement has started from the other end.
BasemenT – Phase2 : Lower basement roof slab is under progress.
Practically no progress in Phase II. F Block structure has already been completed. Around half of brickwork remains to be completed.
If the things keep moving at normal speed, phase 1 can be completed in eight months i.e. by March 2013.
Please feel free to leave your feedback on construction updates at unihomesbuyers@gmail.com or comment on section given below. This will help in circulating accurate and latest update on Unihomes construction progress.
tower B1 -ALMOST COMPLETE ?
NO INSIDE FITTINGS AND GLASS WORK – GATES -WINDOW NOTHING WAS THERE-
ONLY OUTSIDE SE JO DIKHTA HAI BAS VAHI HAI
OR KUCH NAHI